ProjectProject PeriodClient
Samsung C&T P4 Phase 3 Gas Package 2 (P4 Phase 3 closeout)06.2024 - In progressSamsung C&T Corp.
2024-2025 Samsung Electronics piping hook-up program01.2024 - In progressSamsung Electronics Co., Ltd.
2024 chemical piping installation and removal12.2023 - In progressSamsung Electronics Co., Ltd.
2022 DS H3 site utility hook-up package07.2022 - 12.2023Samsung Electronics Co., Ltd.
2022 DS Pyeongtaek site utility hook-up package07.2022 - 12.2023Samsung Electronics Co., Ltd.
Pyeongtaek and Hwaseong chemical piping installation/removal08.2021 - 07.2023Samsung Electronics Co., Ltd.
2021 Hwaseong/Pyeongtaek utility hook-up package01.2021 - 12.2021Samsung Electronics Co., Ltd.
Pyeongtaek P2 lower-level piping hook-up08.2020 - 08.2021Samsung Electronics Co., Ltd.
Samsung Pyeongtaek P2 tool hook-up05.2020 - 12.2021Samsung Electronics Co., Ltd.
Samsung Pyeongtaek P1 tool hook-up04.2020 - 12.2020Samsung Electronics Co., Ltd.
Hwaseong H2 tool hook-up04.2019 - 12.2020Samsung Electronics Co., Ltd.
Hwaseong H1 tool hook-up04.2018 - 03.2019Samsung Electronics Co., Ltd.
Samsung C&T P4 Phase 3 Gas Package 2 (P4 Phase 3 closeout)
Project Period:
06.2024 - In progress
Client:
Samsung C&T Corp.
2024-2025 Samsung Electronics piping hook-up program
Project Period:
01.2024 - In progress
Client:
Samsung Electronics Co., Ltd.
2024 chemical piping installation and removal
Project Period:
12.2023 - In progress
Client:
Samsung Electronics Co., Ltd.
2022 DS H3 site utility hook-up package
Project Period:
07.2022 - 12.2023
Client:
Samsung Electronics Co., Ltd.
2022 DS Pyeongtaek site utility hook-up package
Project Period:
07.2022 - 12.2023
Client:
Samsung Electronics Co., Ltd.
Pyeongtaek and Hwaseong chemical piping installation/removal
Project Period:
08.2021 - 07.2023
Client:
Samsung Electronics Co., Ltd.
2021 Hwaseong/Pyeongtaek utility hook-up package
Project Period:
01.2021 - 12.2021
Client:
Samsung Electronics Co., Ltd.
Pyeongtaek P2 lower-level piping hook-up
Project Period:
08.2020 - 08.2021
Client:
Samsung Electronics Co., Ltd.
Samsung Pyeongtaek P2 tool hook-up
Project Period:
05.2020 - 12.2021
Client:
Samsung Electronics Co., Ltd.
Samsung Pyeongtaek P1 tool hook-up
Project Period:
04.2020 - 12.2020
Client:
Samsung Electronics Co., Ltd.
Hwaseong H2 tool hook-up
Project Period:
04.2019 - 12.2020
Client:
Samsung Electronics Co., Ltd.
Hwaseong H1 tool hook-up
Project Period:
04.2018 - 03.2019
Client:
Samsung Electronics Co., Ltd.

Tool Hook-up / Secondary Piping

ProjectProject PeriodClient
Samsung Electronics Line 16 gas and PCW piping02.2011 - 04.2011Samsung Electronics Co., Ltd.
K2 Project production tool secondary piping12.2010 - 12.2011Samsung Electronics Co., Ltd.
Samsung K2 Project production tool secondary piping01.2010 - 12.2010Samsung Electronics Co., Ltd.
Samsung Hwaseong H1 production tool secondary piping01.2008 - 12.2008Samsung Electronics Co., Ltd.
Samsung Giheung K2 production tool secondary piping01.2008 - 12.2008Samsung Electronics Co., Ltd.
Samsung Hwaseong H1 secondary piping01.2007 - 12.2007Samsung Electronics Co., Ltd.
Giheung S2 Line secondary piping01.2006 - 12.2006Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping09.2004 - 08.2005Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping01.2003 - 12.2003Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping01.2002 - 12.2002Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping01.2001 - 12.2001Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping08.2000 - 12.2000Samsung Electronics Co., Ltd.
Samsung Electronics Line 16 gas and PCW piping
Project Period:
02.2011 - 04.2011
Client:
Samsung Electronics Co., Ltd.
K2 Project production tool secondary piping
Project Period:
12.2010 - 12.2011
Client:
Samsung Electronics Co., Ltd.
Samsung K2 Project production tool secondary piping
Project Period:
01.2010 - 12.2010
Client:
Samsung Electronics Co., Ltd.
Samsung Hwaseong H1 production tool secondary piping
Project Period:
01.2008 - 12.2008
Client:
Samsung Electronics Co., Ltd.
Samsung Giheung K2 production tool secondary piping
Project Period:
01.2008 - 12.2008
Client:
Samsung Electronics Co., Ltd.
Samsung Hwaseong H1 secondary piping
Project Period:
01.2007 - 12.2007
Client:
Samsung Electronics Co., Ltd.
Giheung S2 Line secondary piping
Project Period:
01.2006 - 12.2006
Client:
Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping
Project Period:
09.2004 - 08.2005
Client:
Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping
Project Period:
01.2003 - 12.2003
Client:
Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping
Project Period:
01.2002 - 12.2002
Client:
Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping
Project Period:
01.2001 - 12.2001
Client:
Samsung Electronics Co., Ltd.
Giheung S2 Project production tool secondary piping
Project Period:
08.2000 - 12.2000
Client:
Samsung Electronics Co., Ltd.

Vacuum Piping

ProjectProject PeriodClient
Production tool hook-up piping installation (vacuum)04.2017 - 03.2018Samsung Electronics Co., Ltd.
Vacuum piping installation and fabrication04.2016 - 03.2017Samsung Electronics Co., Ltd.
Vacuum piping fabrication and installation04.2015 - 03.2016Samsung Electronics Co., Ltd.
Vacuum piping fabrication and installation05.2014 - 03.2015Samsung Electronics Co., Ltd.
Production tool vacuum piping07.2013 - 03.2014Samsung Electronics Co., Ltd.
Production tool vacuum piping08.2012 - 03.2013Samsung Electronics Co., Ltd.
Samsung Hwaseong and Giheung vacuum piping01.2009 - 03.2013Samsung Electronics Co., Ltd.
Production tool hook-up piping installation (vacuum)
Project Period:
04.2017 - 03.2018
Client:
Samsung Electronics Co., Ltd.
Vacuum piping installation and fabrication
Project Period:
04.2016 - 03.2017
Client:
Samsung Electronics Co., Ltd.
Vacuum piping fabrication and installation
Project Period:
04.2015 - 03.2016
Client:
Samsung Electronics Co., Ltd.
Vacuum piping fabrication and installation
Project Period:
05.2014 - 03.2015
Client:
Samsung Electronics Co., Ltd.
Production tool vacuum piping
Project Period:
07.2013 - 03.2014
Client:
Samsung Electronics Co., Ltd.
Production tool vacuum piping
Project Period:
08.2012 - 03.2013
Client:
Samsung Electronics Co., Ltd.
Samsung Hwaseong and Giheung vacuum piping
Project Period:
01.2009 - 03.2013
Client:
Samsung Electronics Co., Ltd.

Other Work

ProjectProject PeriodClient
Hynix Semiconductor wastewater treatment facility repairs10.2010 - 10.2010Hynix Engineering Co., Ltd.
Hynix Semiconductor Ami dormitory kitchen upgrades09.2010 - 09.2010Hynix Semiconductor Inc.
Hynix Semiconductor M7A UPW, TMAH, and WWT system upgrades04.2010 - 08.2010Hynix Engineering Co., Ltd.
SB LiMotive Ulsan plant hook-up03.2010 - 09.2010SB LiMotive Co., Ltd.
Siltron ASC equipment drain piping and related work01.2010 - 12.2010Siltron Inc.
National NanoFab Center box furnace utility hook-up12.2009 - 06.2010National NanoFab Center
LG Display P6 Cell DI recycle piping and related work12.2009 - 02.2010LG Display Co., Ltd.
Hynix Semiconductor CDA line piping insulation and related work10.2009 - 12.2009Hynix Engineering Co., Ltd.
National NanoFab Center chemical and stocker (alkali/acid) exhaust duct installation09.2009 - 09.2009National NanoFab Center
LG Display P5 TFT CVD #7 and #8 N2 hook-up and related work08.2009 - 11.2009LG Display Co., Ltd.
Green Cross Ochang plant CIP secondary piping07.2008 - 12.2008Green Cross Corp.
Green Cross secondary equipment hook-up01.2008 - 12.2008Green Cross Corp.
Hynix Semiconductor wastewater treatment facility repairs
Project Period:
10.2010 - 10.2010
Client:
Hynix Engineering Co., Ltd.
Hynix Semiconductor Ami dormitory kitchen upgrades
Project Period:
09.2010 - 09.2010
Client:
Hynix Semiconductor Inc.
Hynix Semiconductor M7A UPW, TMAH, and WWT system upgrades
Project Period:
04.2010 - 08.2010
Client:
Hynix Engineering Co., Ltd.
SB LiMotive Ulsan plant hook-up
Project Period:
03.2010 - 09.2010
Client:
SB LiMotive Co., Ltd.
Siltron ASC equipment drain piping and related work
Project Period:
01.2010 - 12.2010
Client:
Siltron Inc.
National NanoFab Center box furnace utility hook-up
Project Period:
12.2009 - 06.2010
Client:
National NanoFab Center
LG Display P6 Cell DI recycle piping and related work
Project Period:
12.2009 - 02.2010
Client:
LG Display Co., Ltd.
Hynix Semiconductor CDA line piping insulation and related work
Project Period:
10.2009 - 12.2009
Client:
Hynix Engineering Co., Ltd.
National NanoFab Center chemical and stocker (alkali/acid) exhaust duct installation
Project Period:
09.2009 - 09.2009
Client:
National NanoFab Center
LG Display P5 TFT CVD #7 and #8 N2 hook-up and related work
Project Period:
08.2009 - 11.2009
Client:
LG Display Co., Ltd.
Green Cross Ochang plant CIP secondary piping
Project Period:
07.2008 - 12.2008
Client:
Green Cross Corp.
Green Cross secondary equipment hook-up
Project Period:
01.2008 - 12.2008
Client: